Slide 31 of 125
Notes:
The other shuttle Phase-B design team -- McDonnell-Douglas and Martin Marietta -- presented
its final design on June 30, 1971. The Martin Marietta booster was derived from an alternative
“Spacemaster” booster concept. All landing jet engines were installed inside the forward canard
wing to improve the center of gravity, to compensate for the huge mass of the ascent propulsion
system which consisted of thirteen Space Shuttle Main Engines. The high-mounted aft wing with
wing tips was chosen to provide the least interference with the orbiter at launch while still
producing adequate stability for the booster. The Martin Marietta booster was expected to
provide a higher degree of directional stability, except during the subsonic part of the flight
and during landing, when the General Dynamics low-wing design would be less sensitive to crosswinds.
Unlike North American Rockwell, McDAC settled for a metallic thermal protection system on the
shuttle orbiter. Titanium, nickel and columbium materials would have been used. In most other
respects, the McDAC and NAR Phase B orbiters were quite similar. Both featured a large delta
wing plus single vertical stabilizer fin, an 18.3 * 4.57-meter cargo bay, two Space Shuttle
Main Engines for propulsion and RL-10s for maneuvering in space.
McDonnell-Douglas/Martin Marietta shuttle flight plan. The staging maneuver was at 63.8km
altitude. The booster's engines would have to burn 1,378.3t of LOX/LH2 propellants to accelerate
the vehicle to a velocity of 3300m/s. The orbiter's twin engines would have used another 241,648kg
of propellants to reach orbit.
McDonnell-Douglas shuttle orbiter with sortie module. NASA also planned a series of
pressurized and unpressurized experiment modules for the space station and space shuttle. They
would be used for carrying space station logistics, as free-flying experiment carriers and other
purposes. As the space station was postponed, the experiment module gradually evolved into a
“sortie lab” for the shuttle, essentially transforming it into a mini-space station for flights
lasting up to 30 days. General Dynamics received a contract to study space station experiment
modules in August 1969 which eventually morphed into a shuttle “Research and Applications
Module” (RAM). The General Dynamics RAM contract was extended in April 1971 but NASA was
unable to afford the $1-billion cost in the end. The “Spacelab” project was finally farmed out
to the European Space Research Organization in June 1972.
McDonnell-Douglas shuttle orbiter & Modular Space Station (MSS). Another shuttle payload
was NASA's space station. NASA awarded a series of Phase-B station extension contracts to McDAC
and North American Rockwell in March 1971, to study modular space station configurations that
could be launched by the shuttle. The initial goal was now a 6-man space station that would
have required nine shuttle assembly flights.
| 1979 | 1980 | 1981 | 1982 | 1983 | 1984 | 1985 | 1986 | 1987 | 1988 | TOTAL |
TOTAL SHUTTLE FLIGHTS: | 10 | 15 | 20 | 30 | 40 | 50 | 60 | 70 | 75 | 75 | 445 |
NASA's Phase B Shuttle flight plan called for 445 missions over ten years. Only 15.73% of the
flights would involve manned space station assembly & logistics, 42.25% would be dedicated to
deployment of NASA satellites and space probes and another 34.61% would be reserved for the
military. The remaining 7.41% would be dedicated to OTVs, i.e. “space tugs” transporting cargo
to higher orbits. This mission model was strikingly different from the mid-1969 shuttle Phase
Aplan which assumed the launch manifest would be only 5% unmanned payloads and 95% manned space
station/space base/moonbase support!
(NOTE -- all figures in 1970 $ millions) |
DDT&E |
PROD. |
OPS. |
TOTAL |
TOTAL (1999 $M). |
BOOSTER |
4264 |
|
|
4264 |
18309 |
ORBITER |
3597 |
215 |
|
3812 |
16368 |
MAIN ENGINES: |
|
|
|
|
|
BOOSTER |
255 |
406 |
|
661 |
2838 |
ORBITER |
255 |
68 |
|
323 |
1387 |
FLIGHT TEST: |
|
|
|
|
|
BOOSTER |
238 |
190 |
|
428 |
1838 |
ORBITER |
219 |
164 |
|
383 |
1645 |
OPERATIONS & LAUNCH FACILITIES: |
|
|
|
|
|
BOOSTER |
172 |
|
894 |
1066 |
4577 |
ORBITER |
172 |
|
990 |
1162 |
4989 |
MANAGEMENT & INTEGRATION: |
|
|
|
|
|
BOOSTER |
363 |
15 |
|
378 |
1623 |
ORBITER |
308 |
31 |
|
339 |
1456 |
TOTAL PROGRAM: |
|
|
|
|
|
BOOSTER |
5292 |
611 |
894 |
6797 |
29185 |
ORBITER |
4551 |
478 |
990 |
6019 |
25844 |
TOTAL: |
9843 |
1089 |
1884 |
12816 |
55030 |
According to McDonnell-Douglas' cost estimate from June 1971, the Phase-B shuttle would have
cost about $12.815 billion [1970 rates] over 445 flights in 1972-88. The equivalent life-cycle
cost in 1999 dollars would be about $55 billion. But many observers questioned the accuracy
of those estimates since several key technologies (high-pressure reusable engines, thermal
protection system etc.) were unproven.


Payload capability (without landing jets): 29,484kg into a 185km 28.5 deg. Orbit;
18,144kg into a 185km 90 deg. polar orbit; 11,340kg into a 500km 55 deg. orbit with landing
jets installed on orbiter & 20,411kg without engines.
Cost per mission: $4.5 million. [1970 rates] or $660/kg+ in 1999. 75 missions/year max.
Space station rescue mission capability within 48 hours of emergency call.
Liftoff Thrust: 2,606,810 kgf. Total Mass: 2,106,982 kg. Core Diameter: 11.5 m. Total Length: 85.7 m.
Stage Number: 1. 1 x Shuttle R134C-1 Gross Mass: 1,716,692 kg. Landing Weight: 272,600 kg. Thrust: 29,370-32,233.575 KN. Isp: 442 sec. Burn time: 209 sec.
Isp(sl): 392 sec. Diameter: 11.5 m. Span: 50.6 m. Length: 85.7 m. Propellants: Lox/LH2 No Engines: 12. SSME Study
Stage Number: 2. 1 x Shuttle R134C-2 Gross Mass: 360,650 kg. Empty Mass: 119,000 kg. Thrust (vac): 5,624KN. Isp: 459 sec.
Burn time: 264 sec. Isp(sl): 359 sec. Diameter: 4.6 m. Span: 32.8 m. Length: 53.3 m. Propellants: Lox/LH2 No Engines: 2. SSME Study
"NASA Weighs Reports on Shuttle" -- AW&ST 1971/June 7/p.55
”Space Shuttle” -- Dennis R. Jenkins, 1981, ISBN: 0963397451
“MCDONNELL DOUGLAS FULLY REUSABLE SHUTTLE” -- J.F.Yardley, McDonnell-Douglas Astronautics Company - East., St.Louis, MO, June 1971
"Spaceflight and Rocketry -- a Chronology”, David Baker:, Facts on File Inc, 1996, ISBN 0-8160-1853-7